Last Updated | 08/16/2022 12:04 PM |
Project Title | Lake Erie Wind Farm / Icebreaker Wind |
Physical Address | View project details and contacts |
City, State (County) | Cleveland, OH 44113 (Cuyahoga County) |
Category(s) | Heavy and Highway, Industrial/Manufacturing |
Sub-Category(s) | Power Plant, Site Development |
Contracting Method | Bids by Invitation |
Project Status | Obtained from a credible source, Awaiting verification, Construction start expected September 2022 |
Bids Due | View project details and contacts |
Estimated Value | $126,000,000 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The project consists of a 20-megawatt demonstration wind farm (six turbines) in the lake northwest of downtown Cleveland. As of August 11, 2022, this project received approval with conditions from the Ohio Power Siting Board and the Ohio Supreme Court has ruled that the project can move forward. Information regarding the selection of an architect and general contractor has not been provided. A firm construction timeline has not been announced.* *Project information, including timeline and contacts, has been obtained through public sources. The content management team continues to pursue additional details; however, the contact(s) listed have yet to disclose or confirm any information. Inquiries should be directed to the contact(s) listed. This project will be issued to bid to a Pre Qualified Select group of General Contractors. |
||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |