Similar Projects
Somers Sanitation Transfer/Recycling Facility Improvements
New Construction
Design
Somers, NY 10589

BSA Bird Island Treatment Facility Secondary System Rehabilitation and Upgrades
Bidding
Less than $30,000,000 est. value
Buffalo, NY 14213

Fishkill Wastewater Treatment Plant Upgrades
Renovation
Bidding
$150,000 to $16,000,000 est. value
Fishkill, NY 12524

Z--Renovate Sewage Treatment Plant Trickling Filter at Castle Point
Renovation
Post-Bid
$1,000,000 to $5,000,000 est. value
Wappingers Falls, NY 12590

2020 O and M Project- Clarifier Replacement
Post-Bid
Niagara Falls, NY 14304

Village of Coxsackie - Wastewater Treatment Plant Upgrade Project
Results
Coxsackie, NY 12051

Wastewater Treatment Plant Upgrades
Results
Morrisville, NY

Woodhull Waste Water Treatment Facility
Construction
Woodhull, NY 14898

WWTP Upgrades
Construction
Less than $1,900,000 est. value
Germantown, NY

Wastewater Treatment Plant Improvements 2A, 2B and 2C
Bidding
Cottekill, NY

Wastewater Treatment Plant Improvements
Post-Bid
Salamanca, NY 14779

Regional Wastewater Treatment Project Contract No. 4 - Montour Falls Force Main and Pump Station
Results
Montour Falls, NY

Wastewater Treatment Plant Screen Upgrade
Construction
Catskill, NY 12414

WPCP Secondary Clarifiers
Renovation
Bidding
Poughkeepsie, NY 12601

Screening and Grit Transport Equipment Improvements, Polymer Equipment Upgrades and Dewatering Equipment Control Upgrades
Post-Bid
Niagara Falls, NY 14304

Last Updated 05/25/2021 12:33 PM
Project Title

Wastewater Treatment Plant Phase I Upgrades

Physical Address View project details and contacts
City, State (County) North Tonawanda, NY 14120   (Niagara County)
Category(s) Sewer and Water
Sub-Category(s) Sewage Treatment Plant
Contracting Method
Project Status Construction Commenced second quarter 2020, Construction Completion Expected third quarter 2021, No Sub Bids Needed
Bids Due View project details and contacts
Estimated Value
Plans Available from
Owner View project details and contacts
Architect View project details and contacts
Description

Work generally consists of the following improvement Wastewater Treatment Plant which addressed as part of this Demolition of a portion of the existing grit removal Providing a grit removal system concrete tank, grit removal grit dewatering concentrated and screw precast concrete building control, electrical equipment and all associated site work accessories and appurtenances, Replacement of various pumping including pumps, controls, electrical equipment and all associated and appurtenances Replacement of existing pressurized gaseous chlorine system With a new vacuum chlorine chlorine system along with ventilation Motor control center upgrades Removal of costing light fixtures furnishing installing replacement energy efficient lighting and lighting controls Project is a Multiple Contract Project consisting of the following prime contracts: 2020-01 -G General Construction 2020-01 -M Construction 2020-01 -E Electrical Construction

Details

Division 02 - Existing Conditions, Subsurface Investigation.
Division 03 - Concrete, Precast Concrete.
Division 04 - Masonry, Unit Masonry.
Division 05 - Metals, Structural Metal Framing, Metal Fabrications.
Division 06 - Wood, Plastics, and Composites, Rough Carpentry.
Division 07 - Thermal and Moisture Protection, Dampproofing and Waterproofing, Thermal Protection.
Division 08 - Openings, Doors and Frames, Windows, Hardware.
Division 09 - Finishes, Painting and Coating.
Division 10 - Specialties, Signage, Compartments and Cubicles, Emergency Aid Specialties, Fire Protection Specialties, Storage Assemblies.
Division 11 - Equipment, Laboratory Equipment.
Division 14 - Conveying Equipment.
Division 21 - Fire Suppression, Fire-Extinguishing Systems.
Division 22 - Plumbing, Instrumentation and Control for Plumbing, Plumbing Piping, Plumbing Equipment, Plumbing Fixtures.
Division 23 - Heating, Ventilating, and Air Conditioning (HVAC), Instrumentation and Control for HVAC, HVAC Air Distribution.
Division 26 - Electrical, Instrumentation and Control for Electrical Systems, Interior Lighting, Emergency Lighting, Exit Signs, Exterior Lighting.
Division 27 - Communications, Structured Cabling, Data Communications, Voice Communications, Distributed Audio-Video Communications Systems.
Division 28 - Electronic Safety and Security, Electronic Access Control and Intrusion Detection, Access Control, Intrusion Detection, Electronic Surveillance, Electronic Detection and Alarm.
Division 31 - Earthwork, Earthwork Methods.
Division 32 - Exterior Improvements, Flexible Paving, Rigid Paving, Curbs, Gutters, Sidewalks, and Driveways, Fences and Gates, Turf and Grasses.
Division 33 - Utilities, Water Utilities, Storm Drainage Utilities, Electrical Utilities, Communications Utilities.
Division 44 - Pollution and Waste Control Equipment, Common Work Results for Pollution and Waste Control Equipment, Air Pollution Control, Noise Pollution Control, Odor Control, Water Pollution Control Equipment, Solid Waste Control and Reuse, Waste Thermal Processing Equipment, Fluidized Bed Combustion Equipment, Rotary Kiln Incinerators, Pyrolysis Equipment, Hazardous Waste and Medical Waste Incinerators, Heat Recovery Equipment for Waste Thermal Processing, Synthesis Gas Cleanup and Handling Equipment.

Bidder's List View project details and contacts
Prospective Bidders View project details and contacts
Project Documents
 Engineered Spec Sheet
 Architectural Plans
 Other Documents