Last Updated | 03/30/2023 10:13 AM |
Project Title | Indian River Road Phase VII-A-PG100217 & VII-B-PG100213 - City of Virginia Beach |
Physical Address | View project details and contacts |
City, State (County) | Virginia Beach, VA 23456 (Virginia Beach City County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Site Development |
Contracting Method | Competitive Bids |
Project Status | Design Development, Construction start expected August 2025 |
Bids Due | View project details and contacts |
Estimated Value | $98,172,200 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | This project has two phases, and they are to be constructed together under one contract. Phase VII-A-PG100217 - VDOT UPC #15829. This is the first phase and will provide two through lanes on the ultimate four-lane right-of-way footprint (2 on 4 configuration) on Indian River Road from Lynnhaven Parkway to Elbow Road Extended (PG100529), a distance of approximately 2.1 miles. The two lanes constructed in Phase VII-A will serve as the future southbound lanes in the ultimate four-lane divided roadway configuration. The typical roadway section includes multi-use paths, on-road bicycle accommodations, streetlights, landscaping, and noise barriers (where warranted in their ultimate locations on both sides of the roadway). The majority of the project corridor will be realigned further east, away from adjacent Stumpy Lake, wetlands, and the floodplain. Phase VII-B-PG100213 - VDOT UPC #110804. This project will provide the additional two lanes (northbound) of the Indian River Road Phase VII-A section from Lynnhaven Parkway to Elbow Road Extended, a distance of approximately 2.1 miles. The construction of the additional two lanes will complete the ultimate four-lane divided roadway configuration on Indian River Road. The typical roadway section includes multi-use paths, on-road bicycle accommodations, streetlights and landscaping (noise barriers previously constructed in Phase VII-A). The majority of the project corridor will be realigned further east, away from adjacent Stumpy Lake, wetlands, and the floodplain. Project is included City of Virginia Beach FY 2022-2027 CIP. As of November 3, 2022, a design team has been identified. Construction timeline is from August 2025 (NTP) to April 2028. |
||||
Details |
|
||||
Bidder's List | View project details and contacts | ||||
Prospective Bidders | View project details and contacts | ||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |