Similar Projects
Rivian Automotive East Atlanta Megasite Building Vertical Construction / Stanton Springs North
New Construction, Infrastructure - 12,000,000 SF
Conception
$5,000,000,000 CJ est. value
Social Circle, GA 30025

Alcovy River Gravity Sewer - City of Monroe
Infrastructure
Conception
$4,000,000 CJ est. value
Monroe, GA 30655

Grove at Rosebud - Phase 2
New Construction, Infrastructure
Design
$6,000,000 CJ est. value
Loganville, GA 30052

Jacks Creek Landing
New Construction, Infrastructure
Design
$105,000,000 CJ est. value
Monroe, GA 30655

Whataburger / Monroe
New Construction, Infrastructure - 3,746 SF
Bidding
$1,500,000 CJ est. value
Monroe, GA 30655

USCG National Multiple Award Construction Contract (NMACC III)
Term Contract
Post-Bid
$25,000,000 CJ est. value
Seattle, WA 98174

Piedmont Regional Industrial Park Site Grading
Infrastructure
Post-Bid
GA

Agriculture Meter Installation
Infrastructure
Results

Water Meter Replacement Project
Infrastructure
Results
$95,000 est. value
Helen, GA

Brand Road C-Store / Loganville
New Construction, Infrastructure - 3,237 SF
Construction
$2,227,627 CJ est. value
Loganville, GA 30052

Lake Carlton Road Townhomes
New Construction, Infrastructure
Pending Verification
$70,000,000 CJ est. value
Loganville, GA 30052

Twin Forks
New Construction, Infrastructure
Pending Verification
$22,500,000 CJ est. value
Loganville, GA 30052

Spring Street Tank 10" Water Main Loop (Tank to CSX Bore on E Hightower) - City of Social Circle
Infrastructure
Conception
$350,000 CJ est. value
Social Circle, GA 30025

SR 83 at Polecat Creek 1 Mi Nw of Good Hope
Demolition, New Construction, Infrastructure
Design
$2,000,000 CJ est. value
Good Hope, GA 30641

Water System Project
Infrastructure
Post-Bid
GA

Last Updated 01/09/2023 11:34 AM
Project Title

SR11 and SR12 Roundabout - DOT Relocation - Natural Gas Pipeline System

Physical Address View project details and contacts
City, State (County) Social Circle, GA 30025   (Walton County)
Category(s) Heavy and Highway, Sewer and Water
Sub-Category(s) Site Development, Water Lines
Contracting Method Competitive Bids
Project Status Contract Award, Construction start expected January 2023
Bids Due View project details and contacts
Estimated Value $150,000 [brand] Estimate
Plans Available from Civil Engineer
Owner View project details and contacts
Architect View project details and contacts
Description

The work consists of providing all labor, tools, skills, equipment and all incidental materials not supplied by the city for the construction of approximately 2,500 feet of 6-inch steel gas main, 400 feet of 4-inch steel gas main, and one commercial gas service along and within the right of way of SR 11 and SR 12 at a new Roundabout near Covington Georgia.Bidders shall inform themselves concerning Georgia Laws, and comply with same. Each proposal or bid must be accompanied by a cashier's check or certified check on a duly organized bank made payable to the City of Covington or a bidding bond executed by the bidder, and surety company authorized to transact business in the State of Georgia, in the sum of not less than five percent (5%) of the total amount of the bid. Said check or bond will be returned to the unsuccessful bidder as soon as the contract or contracts have been awarded and to the successful bidder as soon as he has executed the contract or contracts and furnished the necessary bonds, same having been approved by the City's attorney. All bids must be made out on the proposal form furnished in the contract documents, in accordance with the instructions in the Information for Bidders. No interlineations, additions or deletions shall be made in the proposal form by the bidder.The successful bidder will be furnished, free of charge, three (3) sets of plans and contract documents.No bid may be withdrawn after the scheduled closing time for receiving bids for a period of ninety (90) days. The Owner reserves the right to reject any or all bids; to waive formalities; re-advertise; and to reduce or add to the contract from time to time.

Details

2,500 SF.
Division 33 - Utilities, Instrumentation and Control for Utilities, Water Utilities, Water Utility Distribution Piping, Water Utility Distribution Equipment, Disinfecting of Water Utility Distribution, Water Utility Storage Tanks.

Bidder's List View project details and contacts
Prospective Bidders View project details and contacts
Project Documents
 Engineered Spec Sheet
 Architectural Plans
 Other Documents