Similar Projects
Last Updated | 12/27/2023 02:02 AM |
Project Title | South 28th St Dust Mitigation |
Physical Address | View project details and contacts |
City, State (County) | Springfield, OR 97477 (Lane County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Sidewalks/Parking Lot, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected January 2024 |
Bids Due | View project details and contacts |
Estimated Value | $1,955,648 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | **As of December 26, 2023, project was awarded to Emery & Sons Construction Group, LLC with awarded amount is 1,955,647.75.** This is a Federal-Aid Project. FAP No. STP C039(085) Scope of Work: Grading, Drainage, Paving & Signing Req. Approx. 350 HR Training; 223 FT2 Temp Sign; 1,540 HR Flag; 1 EA Portable Traffic Sig; 1,363 Ft Ped Channelization; 277 Ft Temp Fence; 1,624 Ft Sed Fence; 10 EA Soil Test; 500 Ton Contam Soil Disp; 3,582 YD3 General Excavation; 500 YD2 Subg Stabilization; 5,228 YD2 Subg Geotextile; 788 Ft Mainline Video Insp; 440 YD2 Subsurf Drains; 55 Ft 12 Inch Culv; 327 Ft 10 Inch Stm Pipe; 460 Ft 12 Inch Stm Pipe; 187 Ft Trench Drain; 2 EA Manhole; 1 EA Flow Contr Manhole; 7 EA Conc Inlet; 14 EA Adj Boxes; 4 EA Minor Adj Manhole; 4,113 Ton Aggr Base; 1,650 Ton Acp Mixture; 12 EA AC Approaches; 101 YD2 Rein Conc Pvmt; 4 EA Flex to Rig Pvmt Transit; 2,615 Ft Conc Curb; 5,579 FT2 Conc Driveway; 8,928 FT2 Conc Walk; 4 EA Curb Ramp; 74 FT2 Trunc Dome; 2,563 Ft Pvmt Marking Durable; 90 FT2 Pvmt Bar; 3 EA Crosswalk Closure; 7 EA Bioretention Ponds; 250 YD3 Topsoil; 119 YD3 Water Quality Mix; 2,220 EA Shrubs; 277 Ft Remv Rebuild Fence. Project Cost Range $1 Mil - $2 Mil *The Value for This Project Is Based on a Financial Range. The Value Is Listed as the Highest Possible Cost From the Range Provided by a Stakeholder or Official Project Document. Bidder Acknowledges That This Is a Public Improvement Contract Subject to Prevailing Wage Rate Law Under Ors 279c.800 to 279c.870, and Agrees That Bidder and All Subcontractors Will Comply With the Requirements of Ors 279c.838 and 279c.840. Completion Time December 31, 2024 All Bids shall be accompanied by a Bid guaranty in the amount of 10% of the total amount of the Bid. Each bid must be submitted on the required forms and be accompanied by Bid guaranty, in the form of a cashier's check, certified check, irrevocable letter of credit issued by an insured institution as defined in ORS 706.008 All Subcontractors Must Be Registered With the Construction Contractors Board or Licensed by the State Landscape Contractors Board in Accordance With Ors Chapter 701 Before the Subcontractors Commence Work Under the Contract. Lane County reserves the right to claim up to the policy limits. All coverages are Primary and Non-Contributory with any other insurance and self-insurance Question Deadline 11/09/2023 at 3:00 PM PT |
||||||||
Details |
|
||||||||
Bidder's List | View project details and contacts | ||||||||
Prospective Bidders | View project details and contacts | ||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |