Last Updated | 12/07/2022 10:52 AM |
Project Title | Phase/Reach 5 Truck Haul - Tranche Two |
Physical Address | View project details and contacts |
City, State (County) | N Topsail Bch, NC 28460 (Onslow County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Dock/Pier/Marine, Site Development |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected February 2023 |
Bids Due | View project details and contacts |
Estimated Value | $8,621,653 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | *As of December 7, 2022, a general contractor has been awarded. Construction is scheduled to begin in February 2023. The Town of North Topsail Beach (NTB) is seeking bids from qualified contractors for construction of the Phase/Reach 5 Truck Haul - Tranche Two. The Base Bid project includes placing ~290,000 cubic yards (cy) of beach compatible material along ~6,800 feet of shoreline on the southern portion of Reach 5. Two upland mines are included in the bid package and other potential beach compatible sand mines can also be used (subject to engineer and permitting approval). Alternate/Discretionary bid items for a Reach 4 truck haul nourishment are also included. The Work will be substantially completed on or before _April 30, 2024__, NTB reserves the right to reject any and all bids. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |